The screen is used to verify that a piece meets all Post Pour requirements.

You access QC Verification by Bed from the Quality Control > QC Verification by Bed, click on the bed you would like to view, then click on the Post Pour tab (Green Box see Figure 1).

Figure 1

List Screen

Before you can start working on the individual check list they need to be created, you can create all of the checklists at once if you click on the Start All button (Green Box see Figure 2). If you want to create only one check list at a time, you can click on the arrow in the circle button (Yellow Box see Figure 2). If something went wrong or you want to start over, you can click on the Delete button (Red Box see Figure 2)

Figure 2

After the check list was created you can edit the check list by clicking on the Edit button (Blue Box see Figure 3).

If you would like to delete a check list you can click on the Delete button (Yellow Box see Figure 3).

If you would like to add a picture to the check list, click on the Add Picture button (Orange Box see Figure 3)

Figure 3

Edit Screen

The edit details are broken into five columns.

Unchecked: Items that need to be looked at.

NA: Doesn’t apply to the piece in question.

Pass: The issue has passed inspection.

Fail: The Issue hasn’t passed inspection.

Fixed: The problem found has been fixed.

If you need to add a picture to the check list item click on the Picture button (Green Box see Figure 4).

When you have completed the check list item you can click on the Save (Red Box see Figure 4), Save and Close (Yellow Box see Figure 4) or Prev/Next Buttons (Orange Box see Figure 4).

If there is a problem with the piece and you need to create a Production NCR, click on the Create NCR button (Black Box see Figure 4).

Figure 4

Complete Check Lists

After all of the pieces have undergone the Post Pour Check List (See Figure 5) they need to be marked as completed, you can do this in one of two ways.

  1. By clicking on the check mark buttons (Green Box see Figure 5) for each line.
  2. By clicking on the Complete (Orange Box see Figure 5) for all of the beds.

Figure 5

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article